Artifacts > Test Artifact Set > Test Plan > Checkpoints

    • The test plan clearly identifies the scope of the test effort, by stating the following:
      • stages and types of test to be implemented and executed
      • target-of-test features or functions to be tested / not tested (if appropriate)
      • any assumptions, risks, or contingencies which may affect or impact the test effort
    • The test plan clearly identifies the artifacts (and version) used to generate the contents of the test plan.
    • Each project requirement (as stated in use cases or the supplemental specifications) has at least one associated requirement for test or a statement justifying why it is not a requirement for test.
    • All the requirements for test have been identified and prioritized for each of the different types of tests to be implemented and executed.
    • A clear and concise test strategy is documented for each type of test to be implemented and executed. For each test strategy, has the following information been clearly stated:
      • the name of the test and its objective
      • a description of how the test will be implemented and executed
      • a description of the metrics, measurement methods, and criteria to be used evaluate the quality of the target-of-test and completion of the test
    • All the resources needed to successfully implement and execute testing have been identified, including hardware, software, and personnel.
    • The test plan contains a schedule or list of milestones identifying the major project and test related activities (start and end dates, and / or effort).
    • The test plan identifies the artifacts created by the test activities, when the artifacts are made available, how they will be distributed, their content, and how they should be used.
Feedback © 2014 Polytechnique Montreal